Preliminary Planning and Scheduling

  • Plan in advance
  • Delete unnecessary work
  • Determine expected radiation levels
  • Estimate collective dose
  • Sequence jobs
  • Schedule work
  • Select a trained and experienced work force
  • Identify and coordinate resource requirements

Preparation of Technical Work Documents

  • Include special radiological control requirements in technical work documents
  • Perform ALARA pre-job review
  • Plan access to and exit from the work area
  • Provide for service lines (air, welding, ventilation)
  • Provide communication (sometimes includes closed-circuit television)
  • Remove or shield sources of radiation
  • Plan for installation of temporary shielding
  • Decontaminate
  • Work in lowest radiation levels
  • Perform as much work as practicable outside radiation areas
  • State requirements for standard tools
  • Consider special tools, including robots
  • State staging requirements for materials, parts and tools
  • Incorporate Radiological Control Hold Points
  • Minimize discomfort of workers
  • Revise estimates of person-rem
  • Prepare Radiological Work Permits (RWPs)

Temporary Shielding

  • Design shielding to include stress considerations
  • Control installation and removal by written procedure
  • Inspect after installation
  • Conduct periodic radiation surveys
  • Prevent damage caused by heavy lead temporary shielding
  • Balance radiation exposure received in installation against exposure saved by installation
  • Shield travel routes
  • Shield components with abnormally high radiation levels early in the maintenance period
  • Shield position occupied by worker
  • Perform directional surveys to improve design of shielding by locating source of radiation
  • Use mock-ups to plan temporary shielding design and installation
  • Consider use of water-filled shielding

Rehearsing and Briefing

  • Rehearse
  • Use mock-ups duplicating working conditions
  • Use photographs and videotapes
  • Supervisors conduct briefings of workers

Performing Work

  • Comply with technical work documents and RWPs
  • Post radiation levels
  • Keep excess personnel out of radiation areas
  • Minimize radiation exposure
  • Supervisors and workers keep track of radiation exposure
  • Workers assist in radiation and radioactivity measurements
  • Delegate radiological control monitoring responsibilities
  • Evaluate use of fewer workers
  • Reevaluate reducing radiation exposures
  • Compare actual collective dose against pre-job estimate
  • Review work practices to see if changes will reduce dose
  • Coordinate personnel at the job site to reduce nonproductive time